Notification maintenance EnergyStock
13
Nov
2019
11:53
EnergyStock will carry out its planned maintenance work from gas day Thursday November 14th 2019 up to and including gas day Saturday November 16th 2019. During the whole maintenance period there will be no gas flow.
EnergyStock requests shippers to send in zero nominations for the maintenance period.
The work will start on Thursday November 14th 2019 at 06:00h LET. At 06:00h LET on Sunday November 17th 2019, the work is expected to be finished and the gas flow will be resumed.
Contact details for further information:
Account manager EnergyStock during office hours at: +31 50 521 3194
EnergyStock Dispatching Centre 24/7 at: +31 50 521 1510
Message data | |
---|---|
messageType | gas |
messageId | ES_21X000000001057C-001508_001 |
eventStatus | Active |
eventType | Transmission system unavailability |
eventStart | 2019-11-14 06:00:00 |
eventStop | 2019-11-17 06:00:00 |
unavailabilityType | Planned |
unavailabilityReason | Planned maintenance |
publicationDateTime | 2019-11-13 11:53:59 |
unitMeasure | KWh/h |
unavailableCapacity | 18565000 |
availableCapacity | 0 |
technicalCapacity | 18565000 |
injection | 0 |
withdrawal | 0 |
remarks | |
balancingZone(s) |
|
affectedAsset | ZUIDW_ZWD-GRID - 21Z000000000215Y |
marketParticipant(s) |
EnergyStock B.V. - 21X000000001057C
|