Construction almost complete

01 Aug 2010

The construction of the Zuidwending storage facility runs on schedule. The gas installation is technically complete and is currently in the phase of testing and commissioning. The four caverns are near completion as well. The first two caverns are filled with gas and are made ready for operation. The so called "snubbing" operation for these two caverns has been done. That means that the tubings for leaching and and gas fill are removed. The third and fourth cavern are currently being filled with gas. For more information about the construction we would lik to refer you to our project website: www.agbzw.nl.


On May 20, 2014 Gasunie Zuidwending changed its company name to EnergyStock. This news item was posted by EnergyStock’s predecessor Gasunie Zuidwending before the name change.